03/26/2024 Update
Greetings neighbors,
New Work
We will commence paving along Horton Street, Sherwin Ave and Halleck Street starting April 1st. In addition, the Halleck sidewalk extension will be taking place. Here is the anticipated schedule, please come back here for any updates:
- April 1st – Horton Street paving and Halleck sidewalk extension/ramp
- April 2nd & 3rd – Sherwin paving
- April 4th – Halleck paving
During this time access to roadways will be down to one lane. Driveways will not be impeded, but you may experience some delay in access.
Ongoing work
We continue to work on the Level 4 improvements. Please see the below updated schedule:
Schedule of upcoming work, subject to change:
- 2/20 – 4/2: Construction of Level 4 improvements will commence on location A.
- 4/2 – 4/17: Construction of Level 4 improvements will commence on location B.
- 4/17 – 5/10: Construction of Level 4 improvements will commence on location D.
- 5/10-5/24: Construction of Level 4 improvements will commence on location E.
- 4/2-5/24: Construction of Level 4 improvements will commence on locations C, F, G & H.
Any changes to schedule will be updated here on our website. Please reach out to desiree.morgan@quarterra.com with any questions.